15/16 Greens Renovation & Projects / Fall 2013

Sorry for the lack of blog activity through the season.  Now that project time has begun I will keep a flow of photos and information heading out to you so we are all on the same page.

First I would like follow up on the 12th tee project and how that ended up working quite well.  Photos tell the story as shown below.

finished post Sandy destruction work / sod and prep day before mens member guest

got over 5" of rain on Friday of the member guest

newly reconstructed tee washed out to sea...again

reworked the slopes...hydroseeded

added a drainage path in the lowest area


brought in tee/construction mix for new blue tee area

laid the sod and opened it up again...and of course it rained 2" this night.

but, because of the well built drainage system, it survived with no issues 

and all is well on 12 once again.