"The three most important items for success of a green.
DRAINAGE, DRAINAGE & DRAINAGE."
Drainage, Sunlight & Airflow is probably more accurate...but the point is made.
The rough shaping is now finished on both 15 & 16 and drainage work under way. Both greens drainage systems have improved dramatically, going from near nothing to extensive.
Today, 11/12/13, we had a slight delay due to an unexpected burst of snow. This made the surfaces a little too wet to work on today, but will be fine to continue tomorrow.
as usual...here are some photos:
| drainage "plan" for 16 |
| shooting grades for proper pitch |
| installation process begins |
| lower section of 16 green, herringbone drainage |
| 16 drainage completed |
| upper 16 |
| 15 drainage being installed |
| 15 final rough grade |
| through it all the leaves keep falling... |
| ...and we keep cleaning 'em up. This seems never-ending. Pretty much, 8 hrs a day for 8 weeks |
| 11/12/13 surprise snow |
| Pretty to look at, but that's enough for me. that's our update for today, 11/12/13, hope you enjoy the blog. tune in again soon for more photos of the project. Thanks, John |